| Action Date | Action Description | 
|---|---|
| Sep 30, 2009 | Assent Application Received | 
| Oct 01, 2009 | Administrative Review for Completeness | 
| Oct 06, 2009 | Team Review for Completeness | 
| Oct 06, 2009 | Team Review for Completeness | 
| Oct 06, 2009 | Application Accepted | 
| Oct 22, 2009 | HPHC Historical Preservation No Effect | 
| Oct 26, 2009 | 30 day Public Notice Issued | 
| Nov 04, 2009 | Objections/Comments Received | 
| Nov 24, 2009 | Objections/Comments Received | 
| Nov 25, 2009 | Objections/Comments Received | 
| Nov 25, 2009 | Objections/Comments Received | 
| Nov 26, 2009 | Public Notice End Date | 
| Dec 18, 2009 | Objections/Comments Received | 
| Dec 21, 2009 | Objections/Comments Received | 
| Dec 26, 2009 | Public Notice End Date Extension Granted | 
| Jan 06, 2010 | Engineering Report | 
| Jan 26, 2010 | Biologist Report | 
| Feb 04, 2010 | Supervisor Biologist SignOff | 
| Feb 04, 2010 | Executive Signoff of Staff Reports | 
| Mar 01, 2010 | Ready to Schedule Semi-Monthly Meeting | 
| Mar 01, 2010 | Mail Agenda Notice | 
| Mar 05, 2010 | Continuance Requested | 
| Mar 05, 2010 | Continuance request by applicant granted by Council | 
| Mar 09, 2010 | Semi-Monthly Meeting Date Scheduled | 
| Mar 09, 2010 | Mail Agenda Notice | 
| Mar 09, 2010 | Entry of Appearance Received | 
| Mar 10, 2010 | Ready to Schedule Semi-Monthly Meeting | 
| Apr 06, 2010 | Continuance Requested | 
| Apr 07, 2010 | Continuance request by applicant granted by Council | 
| Apr 09, 2010 | Correspondence Received | 
| Apr 13, 2010 | Semi-Monthly Meeting Date Scheduled | 
| Jun 01, 2010 | Correspondence Received | 
| Aug 11, 2010 | Correspondence Received | 
| Feb 06, 2013 | Correspondence Received | 
| Oct 01, 2013 | Ready to Schedule Semi-Monthly Meeting | 
| Nov 04, 2013 | Mail Agenda Notice | 
| Nov 21, 2013 | Correspondence Received | 
| Nov 26, 2013 | Semi-Monthly Meeting Date Scheduled | 
| Nov 26, 2013 | Continued Application by the Council | 
| Jan 07, 2014 | Ready to Schedule Semi-Monthly Meeting | 
| Jan 07, 2014 | Mail Agenda Notice | 
| Jan 16, 2014 | Geologist Report | 
| Jan 28, 2014 | Semi-Monthly Meeting Held | 
| Jan 28, 2014 | Council Approval Granted | 
| Jan 28, 2014 | Semi-Monthly Meeting Date Scheduled | 
| Mar 03, 2014 | Phone Call | 
| May 01, 2014 | 30 Day Appeal Notification to Owner | 
| May 01, 2014 | Legal Response/Decision | 
| Jul 03, 2014 | Stipulation Package from Biologist | 
| Jul 03, 2014 | Stipulation Package by Engineer | 
| Sep 03, 2014 | Typist for Processing | 
| Sep 03, 2014 | Permit Approved | 
| Sep 04, 2014 | Executive Sign Off | 
| Sep 04, 2014 | Sent to Photo Copy | 
| Sep 19, 2014 | Land Evidence Date | 
| Apr 14, 2016 | Mail Agenda Notice | 
| Apr 26, 2016 | Semi-Monthly Meeting Date Scheduled | 
| Oct 25, 2018 | Additional Information Received | 
| Nov 29, 2018 | Additional Information Received | 
| Dec 11, 2018 | Permit Approved | 
| Apr 17, 2019 | Land Evidence Date |