| Action Date | Action Description | 
|---|---|
| Feb 14, 2011 | Maintenance Certification Request | 
| Feb 15, 2011 | Administrative Review for Completeness | 
| Feb 17, 2011 | Team Review for Completeness | 
| Feb 17, 2011 | Team Review for Completeness | 
| Feb 17, 2011 | Application Accepted | 
| Mar 08, 2011 | HPHC Historical Preservation No Effect | 
| Mar 24, 2011 | Biologist Report | 
| Mar 25, 2011 | Engineering Report | 
| Mar 25, 2011 | Typist for Processing | 
| Mar 25, 2011 | Permit Approved | 
| Mar 28, 2011 | Executive Sign Off | 
| Mar 28, 2011 | Sent to Photo Copy |