| Action Date | Action Description | 
|---|---|
| Apr 25, 2011 | Assent Application Received | 
| Apr 26, 2011 | Administrative Review for Completeness | 
| Apr 26, 2011 | Team Review for Completeness | 
| Apr 26, 2011 | Team Review for Completeness | 
| Apr 26, 2011 | Deficient Application - Owner Notification Sent | 
| Aug 09, 2011 | Deficiency Response Received | 
| Aug 11, 2011 | Team Review for Completeness | 
| Aug 11, 2011 | Team Review for Completeness | 
| Aug 11, 2011 | Application Accepted | 
| Aug 11, 2011 | Category A* (Docks) | 
| Aug 12, 2011 | 30 day Public Notice Issued | 
| Sep 07, 2011 | HPHC Historical Preservation No Effect | 
| Sep 12, 2011 | Public Notice End Date | 
| Sep 16, 2011 | Biologist Report | 
| Sep 16, 2011 | Engineering Report | 
| Sep 20, 2011 | Permit Approved | 
| Sep 20, 2011 | Typist for Processing | 
| Sep 21, 2011 | Executive Sign Off | 
| Sep 21, 2011 | Sent to Photo Copy | 
| Oct 17, 2011 | US Army Corps of Engineers Approval Received | 
| Nov 14, 2011 | Land Evidence Date | 
| Dec 02, 2013 | Commencement of Work Notice received |