| Action Date | Action Description | 
|---|---|
| Jun 20, 2011 | Assent Application Received | 
| Jun 20, 2011 | Administrative Review for Completeness | 
| Jun 22, 2011 | Team Review for Completeness | 
| Jun 22, 2011 | Team Review for Completeness | 
| Jun 22, 2011 | Application Accepted | 
| Jul 13, 2011 | HPHC Historical Preservation No Effect | 
| Sep 14, 2011 | 30 Day Appeal Notification to Owner | 
| Sep 14, 2011 | Additional Information Requested from Applicant | 
| Sep 20, 2011 | Certified Receipt Received | 
| Sep 28, 2011 | Additional Information Received | 
| Sep 29, 2011 | Engineering Report | 
| Sep 30, 2011 | Permit Approved | 
| Sep 30, 2011 | Typist for Processing | 
| Sep 30, 2011 | Biologist Report | 
| Oct 03, 2011 | Executive Sign Off | 
| Oct 03, 2011 | Sent to Photo Copy | 
| Oct 06, 2011 | Land Evidence Date | 
| Mar 13, 2012 | Commencement of Work Notice received |