| Action Date | Action Description | 
|---|---|
| Oct 13, 2015 | Assent Application Received | 
| Oct 14, 2015 | Administrative Review for Completeness | 
| Oct 16, 2015 | Team Review for Completeness | 
| Oct 16, 2015 | Team Review for Completeness | 
| Oct 16, 2015 | Application Accepted | 
| Oct 30, 2015 | 30 day Public Notice Issued | 
| Nov 30, 2015 | Public Notice End Date | 
| Dec 04, 2015 | Additional Information Received | 
| Dec 29, 2015 | HPHC Historical Preservation No Effect | 
| Jan 06, 2016 | Permit Approved | 
| Jan 07, 2016 | Engineering Report | 
| Jan 07, 2016 | Sent to Photo Copy | 
| Jan 08, 2016 | Typist for Processing | 
| Jan 11, 2016 | Executive Sign Off | 
| Jan 11, 2016 | Biologist Report | 
| Jan 11, 2016 | Permit Approved | 
| Feb 08, 2016 | Land Evidence Date |