| Action Date | Action Description | 
|---|---|
| Apr 29, 2019 | Assent Application Received | 
| Apr 29, 2019 | Administrative Review for Completeness | 
| Apr 30, 2019 | Team Review for Completeness | 
| Apr 30, 2019 | Application Accepted | 
| May 10, 2019 | HPHC Review Pending | 
| May 10, 2019 | HPHC Historical Preservation No Effect | 
| Jun 26, 2019 | 30 day Public Notice Issued | 
| Jul 26, 2019 | Public Notice End Date | 
| Aug 02, 2019 | Dock/1.1.6 Review approval | 
| Aug 08, 2019 | Plans Received | 
| Aug 21, 2019 | Comments Received | 
| Sep 20, 2019 | Typist for Processing | 
| Sep 20, 2019 | Executive Sign Off | 
| Sep 20, 2019 | Sent to Photo Copy | 
| Sep 20, 2019 | Permit Approved | 
| Sep 20, 2019 | Biologist Report | 
| Sep 26, 2019 | US Army Corps of Engineers Approval Received | 
| Oct 08, 2019 | Land Evidence Date | 
| Jun 10, 2020 | Modification Request | 
| Jun 15, 2020 | Administrative Review for Completeness | 
| Jul 20, 2020 | Plans Received | 
| Jul 22, 2020 | Bio Team Review for Completeness | 
| Jul 23, 2020 | Project Manager | 
| Jul 31, 2020 | Category A* (Docks) | 
| Jul 31, 2020 | 30 day Public Notice Issued | 
| Aug 11, 2020 | Comments Received | 
| Aug 30, 2020 | Public Notice End Date | 
| Oct 14, 2020 | Dock Meeting Scheduled (Admin) | 
| Oct 23, 2020 | Typist for Processing | 
| Oct 23, 2020 | Executive Sign Off | 
| Oct 23, 2020 | Sent to Photo Copy | 
| Oct 23, 2020 | Modification Approved | 
| Oct 23, 2020 | Engineering Report | 
| Nov 06, 2020 | Land Evidence Date | 
| Mar 01, 2021 | Dock Post-Construction Certification by Engineer received. |