| Action Date | Action Description | 
|---|---|
| Feb 26, 2021 | Freshwater Wetland - Preliminary Determination | 
| Mar 02, 2021 | Administrative Review for Completeness | 
| Mar 05, 2021 | Bio Team Review for Completeness | 
| Mar 05, 2021 | Bio Team Review for Completeness | 
| Mar 05, 2021 | Application Accepted | 
| Mar 08, 2021 | Project Manager | 
| Mar 18, 2021 | HPHC Historical Preservation No Effect | 
| Mar 18, 2021 | HPHC Review Pending | 
| May 07, 2021 | Stipulation Package from Biologist | 
| May 07, 2021 | Typist for Processing | 
| May 07, 2021 | Executive Sign Off | 
| May 07, 2021 | Sent to Photo Copy | 
| May 07, 2021 | Permit Approved | 
| May 07, 2021 | Biologist Report |