| Action Date | Action Description | 
|---|---|
| Mar 15, 2021 | Assent Application Received | 
| Mar 17, 2021 | Administrative Review for Completeness | 
| Mar 24, 2021 | Bio Team Review for Completeness | 
| Mar 24, 2021 | Application Accepted | 
| Mar 24, 2021 | Project Manager | 
| Mar 31, 2021 | HPHC Historical Preservation No Effect | 
| Mar 31, 2021 | HPHC Review Pending | 
| Apr 29, 2021 | Biologist Report | 
| May 05, 2021 | Typist for Processing | 
| May 05, 2021 | Executive Sign Off | 
| May 05, 2021 | Sent to Photo Copy | 
| May 05, 2021 | Permit Approved | 
| May 24, 2021 | Land Evidence Date |