| Action Date | Action Description | 
|---|---|
| Jun 30, 2022 | Freshwater Wetland - Preliminary Determination | 
| Jul 06, 2022 | Administrative Review for Completeness | 
| Jul 11, 2022 | Bio Team Review for Completeness | 
| Jul 11, 2022 | Deficient Application - Owner Notification Sent | 
| Nov 22, 2022 | Deficiency Response Received | 
| Dec 12, 2022 | Bio Team Review for Completeness | 
| Dec 12, 2022 | Application Accepted | 
| Dec 12, 2022 | Project Manager | 
| Jan 11, 2023 | HPHC Historical Preservation No Effect | 
| Mar 06, 2023 | Biologist Report | 
| Mar 23, 2023 | Typist for Processing | 
| Mar 23, 2023 | Executive Sign Off | 
| Mar 23, 2023 | Sent to Photo Copy | 
| Mar 23, 2023 | Permit Approved | 
| Mar 28, 2023 | Permit Mailed | 
| Apr 10, 2023 | Land Evidence Date | 
| Jun 26, 2023 | Commencement of Work Notice received |