| Action Date | Action Description | 
|---|---|
| Aug 02, 2022 | CHA Worksheet received | 
| Aug 02, 2022 | Assent Application Received | 
| Aug 04, 2022 | Administrative Review for Completeness | 
| Sep 08, 2022 | Bio Team Review for Completeness | 
| Sep 08, 2022 | Application Accepted | 
| Sep 20, 2022 | Project Manager | 
| Sep 30, 2022 | Additional Information Received | 
| Oct 26, 2022 | HPHC Historical Preservation Comments/Concerns | 
| Nov 29, 2022 | HPHC Historical Preservation No Effect | 
| Jan 11, 2023 | Biologist Report | 
| Jan 11, 2023 | Engineering Report | 
| Jan 17, 2023 | Typist for Processing | 
| Jan 17, 2023 | Executive Sign Off | 
| Jan 17, 2023 | Sent to Photo Copy | 
| Jan 17, 2023 | Permit Approved | 
| Jan 19, 2023 | Permit Mailed | 
| Feb 22, 2023 | Duplicate Original Assent requested/mailed | 
| Oct 05, 2023 | Land Evidence Date |