| Action Date | Action Description | 
|---|---|
| Aug 22, 2022 | Assent Application Received | 
| Aug 23, 2022 | Administrative Review for Completeness | 
| Aug 24, 2022 | Bio Team Review for Completeness | 
| Aug 24, 2022 | Application Accepted | 
| Aug 24, 2022 | Project Manager | 
| Aug 24, 2022 | Category A* (Docks) | 
| Aug 25, 2022 | 30 day Public Notice Issued | 
| Sep 21, 2022 | HPHC Historical Preservation No Effect | 
| Sep 25, 2022 | Public Notice End Date | 
| Oct 03, 2022 | Biologist Report | 
| Oct 05, 2022 | Typist for Processing | 
| Oct 05, 2022 | Executive Sign Off | 
| Oct 05, 2022 | Sent to Photo Copy | 
| Oct 05, 2022 | Permit Approved | 
| Oct 05, 2022 | Permit Mailed | 
| Oct 11, 2022 | Permit Mailed | 
| Jan 31, 2023 | Land Evidence Date | 
| Jan 16, 2024 | Dock Post-Construction Certification by Engineer received. |