| Action Date | Action Description | 
|---|---|
| Oct 20, 2022 | Assent Application Received | 
| Jan 03, 2023 | Administrative Review for Completeness | 
| Jan 04, 2023 | Project Manager | 
| Jan 04, 2023 | Application Accepted | 
| Jan 05, 2023 | Bio Team Review for Completeness | 
| Jan 17, 2023 | Additional Information Received | 
| Jan 17, 2023 | HPHC Historical Preservation No Effect | 
| May 18, 2023 | Additional Information Received | 
| Jun 20, 2023 | Plans Received | 
| Jun 11, 2024 | Biologist Report | 
| Jun 18, 2024 | Typist for Processing | 
| Jun 18, 2024 | Executive Sign Off | 
| Jun 18, 2024 | Sent to Photo Copy | 
| Jun 18, 2024 | Permit Approved | 
| Jun 21, 2024 | Permit Mailed | 
| Sep 09, 2024 | Duplicate Original Assent requested/mailed | 
| Oct 18, 2024 | Land Evidence Date | 
| Mar 17, 2025 | Commencement of Work Notice received |