| Action Date | Action Description | 
|---|---|
| Jan 03, 2024 | Assent Application Received | 
| Jan 08, 2024 | Administrative Review for Completeness | 
| Jan 09, 2024 | Bio Team Review for Completeness | 
| Jan 16, 2024 | Deficient Application - Owner Notification Sent | 
| May 16, 2024 | Deficiency Response Received | 
| May 22, 2024 | Bio Team Review for Completeness | 
| May 22, 2024 | Application Accepted | 
| May 22, 2024 | Project Manager | 
| Jun 24, 2024 | HPHC Historical Preservation No Effect | 
| Jul 10, 2024 | Biologist Report | 
| Jul 11, 2024 | Typist for Processing | 
| Jul 11, 2024 | Executive Sign Off | 
| Jul 11, 2024 | Sent to Photo Copy | 
| Jul 11, 2024 | Permit Approved | 
| Jul 16, 2024 | Permit Mailed | 
| Oct 08, 2024 | Land Evidence Date |