| Action Date | Action Description | 
|---|---|
| Mar 26, 2024 | Maintenance Certification Request | 
| Apr 03, 2024 | Administrative Review for Completeness | 
| Apr 25, 2024 | Additional Information Received | 
| Apr 25, 2024 | Application Accepted | 
| Apr 25, 2024 | Project Manager | 
| May 20, 2024 | Objections/Comments Received | 
| Jun 27, 2024 | Objections/Comments Received | 
| Jun 28, 2024 | Objections/Comments Received | 
| Jul 01, 2024 | Objections/Comments Received | 
| Jul 05, 2024 | Objections/Comments Received | 
| Jul 08, 2024 | Objections/Comments Received | 
| Jul 30, 2024 | Mail Agenda Notice | 
| Aug 20, 2024 | Geologist Report | 
| Aug 27, 2024 | Council Approval Granted | 
| Aug 27, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Nov 27, 2024 | Typist for Processing | 
| Nov 29, 2024 | Executive Sign Off | 
| Nov 29, 2024 | Permit Approved | 
| Nov 29, 2024 | Permit Mailed | 
| Nov 29, 2024 | Legal Response/Decision | 
| Dec 16, 2024 | Commencement of Work Notice received |