| Action Date | Action Description | 
|---|---|
| Jul 31, 2024 | Assent Application Received | 
| Jul 31, 2024 | Administrative Review for Completeness | 
| Aug 05, 2024 | Project Manager | 
| Aug 05, 2024 | Team Review for Completeness | 
| Aug 05, 2024 | Application Accepted | 
| Feb 24, 2025 | Project Manager | 
| Feb 24, 2025 | Geologist Report | 
| Feb 25, 2025 | Typist for Processing | 
| Feb 25, 2025 | Executive Sign Off | 
| Feb 25, 2025 | Sent to Photo Copy | 
| Feb 25, 2025 | Permit Approved | 
| Mar 03, 2025 | Permit Mailed | 
| Oct 23, 2025 | Commencement of Work Notice received |