| Action Date | Action Description | 
|---|---|
| Sep 16, 2024 | Assent Application Received | 
| Sep 18, 2024 | Administrative Review for Completeness | 
| Sep 23, 2024 | Eng Team Review for Completeness | 
| Sep 23, 2024 | Project Manager | 
| Sep 23, 2024 | Application Accepted | 
| Oct 16, 2024 | HPHC Historical Preservation No Effect | 
| Oct 30, 2024 | 30 day Public Notice Issued | 
| Nov 12, 2024 | US Army Corps of Engineers Project Number received. | 
| Nov 30, 2024 | Public Notice End Date | 
| Jan 14, 2025 | Correspondence Received | 
| Jan 15, 2025 | Supervisor Biologist SignOff | 
| Jan 15, 2025 | Supervisor Engineer SignOff | 
| Jan 15, 2025 | Engineering Report | 
| Jan 15, 2025 | Mail Agenda Notice | 
| Jan 16, 2025 | Executive Signoff of Staff Reports | 
| Jan 28, 2025 | Council Approval Granted | 
| Jan 28, 2025 | Semi-Monthly Meeting Date Scheduled | 
| Aug 22, 2025 | Legal Response/Decision | 
| Aug 22, 2025 | 30 Day Appeal Notification to Owner | 
| Sep 09, 2025 | Stipulation Package by Engineer | 
| Sep 10, 2025 | Typist for Processing | 
| Sep 10, 2025 | Executive Sign Off | 
| Sep 10, 2025 | Sent to Photo Copy | 
| Sep 10, 2025 | Permit Approved | 
| Sep 10, 2025 | Dock Post-Construction Certification by Engineer Required. | 
| Sep 12, 2025 | Permit Mailed |