| Action Date | Action Description | 
|---|---|
| Assent Requirement | |
| Land Evidence Date | |
| Jul 22, 2025 | Assent Application Received | 
| Jul 22, 2025 | CHA Worksheet received | 
| Jul 28, 2025 | Administrative Review for Completeness | 
| Aug 06, 2025 | Bio Team Review for Completeness | 
| Aug 06, 2025 | Application Accepted | 
| Aug 06, 2025 | Project Manager | 
| Aug 25, 2025 | HPHC Historical Preservation Comments/Concerns | 
| Oct 02, 2025 | HPHC Historical Preservation No Effect | 
| Oct 17, 2025 | Additional Information Received | 
| Oct 22, 2025 | Biologist Report | 
| Oct 24, 2025 | Typist for Processing | 
| Oct 24, 2025 | Executive Sign Off | 
| Oct 24, 2025 | Sent to Photo Copy | 
| Oct 24, 2025 | Permit Approved | 
| Oct 28, 2025 | Permit Mailed |