| Action Date | Action Description | 
|---|---|
| Jul 25, 2025 | Freshwater Wetlands Application - New - received | 
| Jul 29, 2025 | Administrative Review for Completeness | 
| Jul 29, 2025 | HPHC Review Pending | 
| Jul 29, 2025 | Eng Team Review for Completeness | 
| Jul 29, 2025 | Bio Team Review for Completeness | 
| Jul 29, 2025 | Project Manager | 
| Jul 29, 2025 | Application Accepted | 
| Aug 20, 2025 | HPHC Historical Preservation Comments/Concerns | 
| Sep 04, 2025 | Additional Information Received | 
| Sep 09, 2025 | Biologist Report | 
| Sep 10, 2025 | Typist for Processing | 
| Sep 10, 2025 | Executive Sign Off | 
| Sep 10, 2025 | Sent to Photo Copy | 
| Sep 10, 2025 | Permit Approved | 
| Sep 10, 2025 | Dock Post-Construction Certification by Engineer Required. | 
| Sep 12, 2025 | Permit Mailed | 
| Sep 23, 2025 | Land Evidence Date |