| Action Date | Action Description |
|---|---|
| Legal Response/Decision | |
| Aug 02, 2021 | Assent Application Received |
| Aug 06, 2021 | Administrative Review for Completeness |
| Aug 06, 2021 | CHA Worksheet received |
| Aug 17, 2021 | Eng Team Review for Completeness |
| Aug 17, 2021 | Application Accepted |
| Aug 17, 2021 | Project Manager |
| Aug 17, 2021 | Category B assigned |
| Sep 16, 2021 | HPHC Historical Preservation No Effect |
| Sep 16, 2021 | HPHC Review Pending |
| Nov 10, 2021 | 30 day Public Notice Issued |
| Nov 23, 2021 | Correspondence Received |
| Dec 10, 2021 | Public Notice End Date |
| Feb 08, 2022 | Additional Information Received |
| Mar 17, 2022 | Plans Received |
| Apr 05, 2022 | Engineering Report |
| Apr 05, 2022 | Biologist Report |
| Apr 06, 2022 | Supervisor Engineer SignOff |
| Apr 06, 2022 | Supervisor Biologist SignOff |
| Apr 07, 2022 | Executive Signoff of Staff Reports |
| Apr 13, 2022 | Water Quality Certification |
| Apr 20, 2022 | Mail Agenda Notice |
| May 10, 2022 | Semi-Monthly Meeting Postponed |
| May 10, 2022 | Mail Agenda Notice |
| May 10, 2022 | Semi-Monthly Meeting Date Scheduled |
| May 24, 2022 | Semi-Monthly Meeting Postponed |
| May 24, 2022 | Semi-Monthly Meeting Date Scheduled |
| Jun 08, 2022 | Mail Agenda Notice |
| Jun 30, 2022 | Council Approval Granted |
| Jun 30, 2022 | Semi-Monthly Meeting Date Scheduled |
| Jul 25, 2022 | Stipulation Package from Biologist |
| Aug 02, 2022 | Stipulation Package by Engineer |
| Aug 02, 2022 | Permit Approved |
| Aug 02, 2022 | Typist for Processing |
| Aug 02, 2022 | Executive Sign Off |
| Aug 02, 2022 | Sent to Photo Copy |
| Aug 02, 2022 | Permit Mailed |
| Jan 17, 2023 | Land Evidence Date |
| Aug 02, 2027 | Assent Expiration Date |