Sep 24, 2025 | Assent Application Received |
Sep 29, 2025 | Administrative Review for Completeness |
Oct 02, 2025 | Bio Team Review for Completeness |
Oct 02, 2025 | Project Manager |
Oct 02, 2025 | Application Accepted |
Oct 10, 2025 | HPHC Historical Preservation No Effect |
Oct 22, 2025 | Additional Information Requested from Applicant |
Oct 28, 2025 | 30 day Public Notice Issued |
Oct 30, 2025 | US Army Corps of Engineers Project Number received. |
Nov 27, 2025 | Public Notice End Date |