| Action Date | Action Description | 
|---|---|
| Jan 22, 1998 | Application Accepted | 
| Jan 26, 1998 | Engineering Report | 
| Jan 27, 1998 | Permit Approved | 
| Jan 27, 1998 | Land Evidence Date | 
| May 03, 2011 | Modification Request | 
| May 03, 2011 | Administrative Review for Completeness | 
| May 04, 2011 | Team Review for Completeness | 
| May 04, 2011 | Team Review for Completeness | 
| May 12, 2011 | 30 day Public Notice Issued | 
| May 16, 2011 | HPHC Historical Preservation No Effect | 
| Jun 12, 2011 | Public Notice End Date | 
| Jul 27, 2011 | Dock Meeting -- Approval | 
| Jul 28, 2011 | Biologist Report | 
| Jul 28, 2011 | Engineering Report | 
| Jul 29, 2011 | Typist for Processing | 
| Jul 29, 2011 | Modification Approved | 
| Jul 29, 2011 | Executive Sign Off | 
| Aug 11, 2011 | US Army Corps of Engineers Approval Received | 
| Nov 09, 2011 | Land Evidence Date |