| Action Date | Action Description | 
|---|---|
| Apr 25, 2007 | Assent Application Received | 
| Apr 26, 2007 | Administrative Review for Completeness | 
| May 02, 2007 | Team Review for Completeness | 
| May 02, 2007 | Team Review for Completeness | 
| May 02, 2007 | Application Accepted | 
| May 22, 2007 | HPHC Historical Preservation No Effect | 
| Jun 29, 2007 | Biologist Report | 
| Jun 29, 2007 | Engineering Report | 
| Jul 02, 2007 | Typist for Processing | 
| Jul 02, 2007 | Executive Sign Off | 
| Jul 02, 2007 | Sent to Photo Copy | 
| Jul 02, 2007 | Permit Approved | 
| Jul 13, 2007 | Land Evidence Date | 
| Oct 20, 2014 | Extension Toll letter mailed | 
| Sep 28, 2016 | Extension Toll letter mailed | 
| Nov 21, 2016 | Extension of Permit Request | 
| Dec 08, 2016 | Enforcement Compliance Inspection Required | 
| Dec 09, 2016 | Process Extension | 
| Dec 09, 2016 | Extension Approved | 
| Mar 09, 2017 | Modification Request | 
| Mar 13, 2017 | Administrative Review for Completeness | 
| Mar 22, 2017 | Team Review for Completeness | 
| Mar 22, 2017 | Application Accepted | 
| Apr 10, 2017 | Plans Received | 
| Apr 25, 2017 | Typist for Processing | 
| Apr 25, 2017 | Executive Sign Off | 
| Apr 25, 2017 | Sent to Photo Copy | 
| Apr 25, 2017 | Modification Approved | 
| Apr 25, 2017 | Biologist Report | 
| Apr 28, 2017 | HPHC Historical Preservation No Effect |