| Action Date | Action Description | 
|---|---|
| Mar 17, 2011 | Assent Application Received | 
| Mar 18, 2011 | Administrative Review for Completeness | 
| Mar 18, 2011 | Team Review for Completeness | 
| Mar 18, 2011 | Team Review for Completeness | 
| Mar 18, 2011 | Application Accepted | 
| Mar 21, 2011 | Biologist Report | 
| Mar 21, 2011 | Engineering Report | 
| Mar 22, 2011 | Typist for Processing | 
| Mar 22, 2011 | Permit Approved | 
| Mar 23, 2011 | Executive Sign Off | 
| Mar 23, 2011 | Sent to Photo Copy | 
| Mar 24, 2011 | Land Evidence Date | 
| Mar 25, 2011 | HPHC Historical Preservation No Effect | 
| Apr 11, 2011 | Commencement of Work Notice received |