| Action Date | Action Description | 
|---|---|
| Feb 26, 2014 | Assent Application Received | 
| Feb 26, 2014 | Administrative Review for Completeness | 
| Mar 04, 2014 | Category A* (Docks) | 
| Mar 06, 2014 | Team Review for Completeness | 
| Mar 06, 2014 | Application Accepted | 
| Mar 12, 2014 | 30 day Public Notice Issued | 
| Mar 25, 2014 | HPHC Historical Preservation No Effect | 
| Apr 12, 2014 | Public Notice End Date | 
| May 16, 2014 | Biologist Report | 
| May 28, 2014 | Typist for Processing | 
| May 28, 2014 | Permit Approved | 
| May 29, 2014 | Executive Sign Off | 
| May 29, 2014 | Sent to Photo Copy | 
| May 30, 2014 | US Army Corps of Engineers Approval Received | 
| Jun 26, 2014 | Land Evidence Date | 
| Jun 26, 2014 | Land Evidence Date |