| Action Date | Action Description | 
|---|---|
| Aug 22, 2014 | Assent Application Received | 
| Aug 25, 2014 | Administrative Review for Completeness | 
| Aug 25, 2014 | Team Review for Completeness | 
| Aug 25, 2014 | Application Accepted | 
| Sep 04, 2014 | Biologist Report | 
| Sep 09, 2014 | Typist for Processing | 
| Sep 09, 2014 | Permit Approved | 
| Sep 10, 2014 | Executive Sign Off | 
| Sep 10, 2014 | Sent to Photo Copy | 
| Sep 15, 2014 | Land Evidence Date | 
| Aug 11, 2016 | Modification Request | 
| Aug 15, 2016 | Application Accepted | 
| Aug 16, 2016 | Biologist Report | 
| Aug 17, 2016 | Typist for Processing | 
| Aug 23, 2016 | Executive Sign Off | 
| Aug 23, 2016 | Sent to Photo Copy | 
| Aug 23, 2016 | Modification Approved | 
| Aug 31, 2016 | Land Evidence Date | 
| Sep 13, 2016 | HPHC Historical Preservation No Effect |