| Action Date | Action Description | 
|---|---|
| Dec 24, 2015 | Assent Application Received | 
| Dec 31, 2015 | Administrative Review for Completeness | 
| Jan 05, 2016 | Team Review for Completeness | 
| Jan 12, 2016 | Deficient Application - Owner Notification Sent | 
| Jan 26, 2016 | Deficiency Response Received | 
| Jan 27, 2016 | Team Review for Completeness | 
| Jan 27, 2016 | Application Accepted | 
| Feb 02, 2016 | HPHC Historical Preservation No Effect | 
| Feb 17, 2016 | Additional Information Requested from Applicant | 
| Mar 03, 2016 | Additional Information Received | 
| Mar 03, 2016 | Plans Received | 
| Mar 10, 2016 | Biologist Report | 
| Mar 11, 2016 | Typist for Processing | 
| Mar 14, 2016 | Executive Sign Off | 
| Mar 14, 2016 | Sent to Photo Copy | 
| Mar 14, 2016 | Permit Approved | 
| Apr 21, 2016 | Land Evidence Date | 
| Dec 30, 2016 | Modification Request | 
| Jan 03, 2017 | Administrative Review for Completeness | 
| Jan 06, 2017 | Team Review for Completeness | 
| Jan 06, 2017 | Application Accepted | 
| Feb 03, 2017 | HPHC Historical Preservation No Effect | 
| Feb 16, 2017 | Biologist Report | 
| Feb 21, 2017 | Typist for Processing | 
| Feb 21, 2017 | Modification Approved |