| Action Date | Action Description | 
|---|---|
| May 19, 2016 | Assent Application Received | 
| May 20, 2016 | Administrative Review for Completeness | 
| Aug 12, 2016 | Correspondence Received | 
| Aug 18, 2016 | Deficient Application - Owner Notification Sent | 
| Aug 18, 2016 | Team Review for Completeness | 
| Sep 14, 2016 | Deficient Application Picked Up | 
| Nov 20, 2018 | Deficiency Response Received | 
| Jan 11, 2019 | Additional Information Received | 
| Feb 28, 2019 | Team Review for Completeness | 
| Mar 01, 2019 | Application Accepted | 
| Apr 24, 2019 | Biologist Report | 
| Apr 25, 2019 | Typist for Processing | 
| Apr 25, 2019 | Executive Sign Off | 
| Apr 25, 2019 | Sent to Photo Copy | 
| Apr 25, 2019 | Permit Approved | 
| May 31, 2019 | Land Evidence Date | 
| Aug 19, 2021 | Monitoring Report | 
| Dec 01, 2021 | Monitoring Report | 
| Apr 22, 2022 | Extension of Permit Request | 
| Apr 28, 2022 | Enforcement Compliance Inspection Required | 
| Apr 28, 2022 | Process Extension | 
| Apr 28, 2022 | Executive Sign Off | 
| Apr 28, 2022 | Extension Approved | 
| Mar 01, 2023 | Monitoring Report | 
| Aug 30, 2024 | Monitoring Report | 
| Sep 17, 2024 | Assent Requirement | 
| Apr 04, 2025 | Correspondence Mailed/Faxed/E-mailed |