| Action Date | Action Description | 
|---|---|
| Oct 07, 2016 | Assent Application Received | 
| Oct 11, 2016 | Administrative Review for Completeness | 
| Oct 11, 2016 | Team Review for Completeness | 
| Oct 11, 2016 | Application Accepted | 
| Nov 10, 2016 | HPHC Historical Preservation No Effect | 
| Dec 01, 2016 | Additional Information Requested from Applicant | 
| Jan 23, 2017 | Plans Received | 
| Mar 10, 2017 | Plans Received | 
| Mar 21, 2017 | Biologist Report | 
| Mar 23, 2017 | Typist for Processing | 
| Mar 23, 2017 | Executive Sign Off | 
| Mar 23, 2017 | Sent to Photo Copy | 
| Mar 23, 2017 | Permit Approved | 
| Sep 06, 2017 | Land Evidence Date |