| Action Date | Action Description | 
|---|---|
| Jan 25, 2017 | Assent Application Received | 
| Jan 25, 2017 | Administrative Review for Completeness | 
| Jan 30, 2017 | Team Review for Completeness | 
| Feb 06, 2017 | Application Accepted | 
| Feb 06, 2017 | Team Review for Completeness | 
| Jun 27, 2017 | HPHC Historical Preservation No Effect | 
| Jan 11, 2018 | Plans Received | 
| Jan 18, 2018 | Plans Received | 
| Apr 11, 2018 | Plans Received | 
| May 01, 2018 | 30 day Public Notice Issued | 
| Jun 01, 2018 | Public Notice End Date | 
| Jul 02, 2018 | Biologist Report | 
| Jul 03, 2018 | Engineering Report | 
| Jul 03, 2018 | Typist for Processing | 
| Jul 03, 2018 | Permit Approved | 
| Jul 03, 2018 | Executive Sign Off | 
| Jul 03, 2018 | Sent to Photo Copy |