| Action Date | Action Description | 
|---|---|
| Aug 27, 2018 | Assent Application Received | 
| Aug 30, 2018 | Administrative Review for Completeness | 
| Aug 30, 2018 | Team Review for Completeness | 
| Sep 05, 2018 | Application Accepted | 
| Sep 05, 2018 | 30 day Public Notice Issued | 
| Sep 17, 2018 | HPHC Historical Preservation No Effect | 
| Oct 05, 2018 | Public Notice End Date | 
| Oct 15, 2018 | Plans Received | 
| Oct 16, 2018 | Typist for Processing | 
| Oct 16, 2018 | Executive Sign Off | 
| Oct 16, 2018 | Sent to Photo Copy | 
| Oct 16, 2018 | Permit Approved | 
| Oct 16, 2018 | Engineering Report |