| Action Date | Action Description | 
|---|---|
| Engineering Report | |
| Dec 26, 2019 | Assent Application Received | 
| Dec 28, 2019 | Administrative Review for Completeness | 
| Jan 02, 2020 | Bio Team Review for Completeness | 
| Jan 14, 2020 | Deficient Application - Owner Notification Sent | 
| Feb 24, 2020 | Deficiency Response Received | 
| Mar 13, 2020 | Eng Team Review for Completeness | 
| Mar 13, 2020 | Application Accepted | 
| Mar 16, 2020 | Project Manager | 
| Mar 19, 2020 | HPHC Historical Preservation No Effect | 
| Mar 19, 2020 | HPHC Review Pending | 
| Mar 20, 2020 | 30 day Public Notice Issued | 
| Apr 20, 2020 | Public Notice End Date | 
| Dec 01, 2021 | Additional Information Received | 
| Feb 13, 2023 | Plans Received | 
| Oct 21, 2024 | Application Cancelled |