| Action Date | Action Description | 
|---|---|
| Oct 13, 2021 | Assent Application Received | 
| Oct 20, 2021 | Administrative Review for Completeness | 
| Oct 28, 2021 | Bio Team Review for Completeness | 
| Oct 28, 2021 | Deficient Application - Owner Notification Sent | 
| Nov 02, 2021 | Deficient Application Picked Up | 
| Feb 28, 2022 | Deficiency Response Received | 
| Mar 07, 2022 | Bio Team Review for Completeness | 
| Mar 07, 2022 | Application Accepted | 
| Mar 07, 2022 | Project Manager | 
| Mar 24, 2022 | HPHC Historical Preservation No Effect | 
| Mar 24, 2022 | HPHC Review Pending | 
| Mar 25, 2022 | Biologist Report | 
| Mar 29, 2022 | Permit Approved | 
| Mar 29, 2022 | Typist for Processing | 
| Mar 29, 2022 | Executive Sign Off | 
| Mar 29, 2022 | Sent to Photo Copy | 
| Mar 29, 2022 | Violation Exists on this Site (C&D Order) | 
| Mar 31, 2022 | Permit Mailed | 
| Aug 15, 2022 | Land Evidence Date |