| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Dec 20, 2021 | Assent Application Received | 
| Dec 22, 2021 | Administrative Review for Completeness | 
| Dec 23, 2021 | Category A* (Docks) | 
| Jan 11, 2022 | Eng Team Review for Completeness | 
| Jan 11, 2022 | Deficient Application - Owner Notification Sent | 
| Jan 11, 2022 | Bio Team Review for Completeness | 
| Jan 20, 2022 | Deficiency Response Received | 
| Feb 16, 2022 | Eng Team Review for Completeness | 
| Feb 16, 2022 | Application Accepted | 
| Feb 16, 2022 | Project Manager | 
| Feb 21, 2022 | 30 day Public Notice Issued | 
| Mar 21, 2022 | Public Notice End Date | 
| May 09, 2022 | Dock/1.1.6 Review approval | 
| May 12, 2022 | Engineering Report | 
| May 27, 2022 | Correspondence Mailed/Faxed/E-mailed | 
| Aug 04, 2022 | US Army Corps of Engineers Approval Received | 
| Aug 15, 2022 | Typist for Processing | 
| Aug 15, 2022 | Executive Sign Off | 
| Aug 15, 2022 | Sent to Photo Copy | 
| Aug 15, 2022 | Permit Approved | 
| Aug 15, 2022 | Permit Mailed | 
| Jan 09, 2023 | Land Evidence Date |