| Dock Post-Construction Certification by Engineer received. | |
| Dec 23, 2022 | Assent Application Received | 
| Dec 28, 2022 | Administrative Review for Completeness | 
| Dec 30, 2022 | Bio Team Review for Completeness | 
| Dec 30, 2022 | Application Accepted | 
| Dec 30, 2022 | Project Manager | 
| Dec 30, 2022 | Category A* (Docks) | 
| Jan 10, 2023 | HPHC Historical Preservation No Effect | 
| Feb 20, 2023 | 30 day Public Notice Issued | 
| Mar 22, 2023 | Public Notice End Date | 
| Apr 06, 2023 | Dock Meeting -- Approval | 
| Apr 07, 2023 | Biologist Report | 
| May 15, 2023 | Typist for Processing | 
| May 15, 2023 | Executive Sign Off | 
| May 15, 2023 | Sent to Photo Copy | 
| May 15, 2023 | Permit Approved | 
| May 19, 2023 | Permit Mailed | 
| Jun 09, 2023 | Land Evidence Date |