| Action Date | Action Description | 
|---|---|
| Aug 09, 2023 | Maintenance Certification Request | 
| Aug 10, 2023 | Administrative Review for Completeness | 
| Aug 23, 2023 | Bio Team Review for Completeness | 
| Aug 23, 2023 | Application Accepted | 
| Aug 23, 2023 | Project Manager | 
| Sep 14, 2023 | HPHC Historical Preservation No Effect | 
| Oct 17, 2023 | Plans Received | 
| Oct 24, 2023 | Biologist Report | 
| Oct 26, 2023 | Typist for Processing | 
| Oct 26, 2023 | Executive Sign Off | 
| Oct 26, 2023 | Sent to Photo Copy | 
| Oct 26, 2023 | Permit Approved | 
| Nov 01, 2023 | Permit Mailed |