| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Aug 17, 2023 | Assent Application Received | 
| Aug 23, 2023 | Administrative Review for Completeness | 
| Aug 25, 2023 | Bio Team Review for Completeness | 
| Aug 25, 2023 | Application Accepted | 
| Aug 25, 2023 | Project Manager | 
| Sep 14, 2023 | HPHC Historical Preservation No Effect | 
| Nov 17, 2023 | 30 day Public Notice Issued | 
| Dec 17, 2023 | Public Notice End Date | 
| Feb 28, 2024 | Dock/1.1.6 Review approval | 
| Feb 28, 2024 | Biologist Report | 
| Mar 01, 2024 | Plans Received | 
| Mar 05, 2024 | Typist for Processing | 
| Mar 05, 2024 | Executive Sign Off | 
| Mar 05, 2024 | Sent to Photo Copy | 
| Mar 05, 2024 | Permit Approved | 
| Mar 08, 2024 | Permit Mailed | 
| Oct 01, 2024 | Land Evidence Date | 
| Oct 25, 2024 | Assent Requirement |