| Action Date | Action Description | 
|---|---|
| Aug 30, 2023 | HPHC Historical Preservation No Effect | 
| Aug 30, 2023 | Dredge Application | 
| Sep 08, 2023 | Administrative Review for Completeness | 
| Oct 26, 2023 | Eng Team Review for Completeness | 
| Oct 26, 2023 | Project Manager | 
| Oct 26, 2023 | Application Accepted | 
| Oct 26, 2023 | 15 day Public Notice Issued | 
| Nov 10, 2023 | Public Notice End Date | 
| Nov 29, 2023 | HPHC Historical Preservation No Effect | 
| Dec 08, 2023 | Engineering Report | 
| Dec 20, 2023 | Typist for Processing | 
| Dec 20, 2023 | Executive Sign Off | 
| Dec 20, 2023 | Sent to Photo Copy | 
| Dec 20, 2023 | Permit Approved | 
| Dec 22, 2023 | Permit Mailed | 
| Jan 23, 2024 | Land Evidence Date | 
| Oct 03, 2024 | US Army Corps of Engineers Approval Received | 
| Feb 28, 2025 | Additional Information Received | 
| Mar 25, 2025 | CAD Cell Fee (initial) received | 
| Mar 25, 2025 | CAD Cell Fee Due - initial (letter) |