| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer Required. | |
| Sep 25, 2024 | Assent Application Received | 
| Oct 01, 2024 | Administrative Review for Completeness | 
| Oct 18, 2024 | Bio Team Review for Completeness | 
| Oct 18, 2024 | Deficient Application - Owner Notification Sent | 
| Nov 25, 2024 | Deficiency Response Received | 
| Nov 27, 2024 | Bio Team Review for Completeness | 
| Nov 27, 2024 | Application Accepted | 
| Nov 27, 2024 | Project Manager | 
| Dec 02, 2024 | 30 day Public Notice Issued | 
| Dec 09, 2024 | HPHC Historical Preservation No Effect | 
| Jan 02, 2025 | Public Notice End Date | 
| Jan 29, 2025 | Dock/1.1.6 Review approval | 
| Jan 29, 2025 | Typist for Processing | 
| Jan 29, 2025 | Executive Sign Off | 
| Jan 29, 2025 | Sent to Photo Copy | 
| Jan 29, 2025 | Permit Approved | 
| Jan 29, 2025 | Biologist Report | 
| Jan 30, 2025 | Permit Mailed | 
| Feb 03, 2025 | Additional Information Received | 
| Mar 25, 2025 | Modification Request | 
| Mar 31, 2025 | Administrative Review for Completeness | 
| Apr 01, 2025 | Bio Team Review for Completeness | 
| Apr 01, 2025 | Project Manager | 
| Apr 01, 2025 | Application Accepted | 
| Apr 10, 2025 | HPHC Historical Preservation No Effect | 
| Apr 17, 2025 | Biologist Report | 
| Apr 22, 2025 | Typist for Processing | 
| Apr 22, 2025 | Executive Sign Off | 
| Apr 22, 2025 | Sent to Photo Copy | 
| Apr 22, 2025 | Modification Approved | 
| Apr 22, 2025 | Modification mailed | 
| Apr 23, 2025 | Permit Mailed | 
| Jun 04, 2025 | Land Evidence Date | 
| Jun 06, 2025 | Duplicate Original Assent requested/mailed | 
| Jun 12, 2025 | Land Evidence Date | 
| Jun 16, 2025 | US Army Corps of Engineers Approval Received |