| Action Date | Action Description | 
|---|---|
| US Army Corps of Engineers Approval Required | |
| Sep 17, 1994 | Application Accepted | 
| Oct 03, 1994 | Engineering Report | 
| Nov 16, 1994 | Permit Approved | 
| Nov 16, 1994 | Land Evidence Date | 
| Aug 19, 2014 | Correspondence Mailed/Faxed/E-mailed | 
| Dec 14, 2022 | Biologist Report | 
| Jan 10, 2023 | Typist for Processing | 
| Jan 10, 2023 | Executive Sign Off | 
| Jan 10, 2023 | Sent to Photo Copy | 
| Jan 11, 2023 | Permit Approved | 
| Jan 24, 2023 | Land Evidence Date | 
| May 01, 2024 | Modification Request | 
| May 08, 2024 | Administrative Review for Completeness | 
| May 13, 2024 | Bio Team Review for Completeness | 
| May 13, 2024 | Application Accepted | 
| May 13, 2024 | Project Manager | 
| May 28, 2024 | HPHC Historical Preservation No Effect | 
| Jun 11, 2024 | 30 day Public Notice Issued | 
| Jul 11, 2024 | Public Notice End Date | 
| Jul 26, 2024 | Additional Information Received | 
| Aug 01, 2024 | Mail Agenda Notice | 
| Aug 06, 2024 | Biologist Report | 
| Aug 27, 2024 | Council Approval Granted | 
| Aug 27, 2024 | Semi-Monthly Meeting Date Scheduled | 
| Sep 06, 2024 | Stipulation Package from Biologist | 
| Jan 06, 2025 | Typist for Processing | 
| Jan 06, 2025 | Modification Approved | 
| Jan 06, 2025 | Modification mailed | 
| Jan 07, 2025 | Executive Sign Off | 
| Jan 28, 2025 | Land Evidence Date | 
| Apr 10, 2025 | Commencement of Work Notice received |