| Action Date | Action Description | 
|---|---|
| Oct 28, 1994 | Application Accepted | 
| Jan 03, 1995 | Engineering Report | 
| Jan 09, 1995 | Permit Approved | 
| Jan 09, 1995 | Land Evidence Date | 
| Feb 13, 2015 | Modification Request | 
| Feb 23, 2015 | Administrative Review for Completeness | 
| Feb 26, 2015 | Team Review for Completeness | 
| Feb 26, 2015 | Biologist Report | 
| Mar 03, 2015 | 30 day Public Notice Issued | 
| Mar 09, 2015 | HPHC Historical Preservation No Effect | 
| Apr 03, 2015 | Public Notice End Date | 
| May 28, 2015 | Additional Information Received | 
| Sep 15, 2015 | Typist for Processing | 
| Sep 16, 2015 | Executive Sign Off | 
| Sep 16, 2015 | Sent to Photo Copy | 
| Sep 22, 2015 | Land Evidence Date |