| Action Date | Action Description | 
|---|---|
| Dock Post-Construction Certification by Engineer received. | |
| Jan 23, 1996 | Application Accepted | 
| Jan 30, 1996 | Biologist Report | 
| Feb 01, 1996 | Permit Approved | 
| Feb 01, 1996 | Land Evidence Date | 
| Apr 28, 2017 | Dock Plate re-issue | 
| Feb 28, 2024 | Modification Request | 
| Mar 04, 2024 | Administrative Review for Completeness | 
| Mar 20, 2024 | Eng Team Review for Completeness | 
| Mar 20, 2024 | Project Manager | 
| Mar 20, 2024 | Application Accepted | 
| Apr 05, 2024 | HPHC Historical Preservation No Effect | 
| Apr 30, 2024 | 30 day Public Notice Issued | 
| May 30, 2024 | Public Notice End Date | 
| Jul 10, 2024 | Dock/1.1.6 Review approval | 
| Sep 10, 2024 | Engineering Report | 
| Oct 24, 2024 | Typist for Processing | 
| Oct 24, 2024 | Executive Sign Off | 
| Oct 24, 2024 | Sent to Photo Copy | 
| Oct 24, 2024 | Modification Approved | 
| Oct 24, 2024 | Modification mailed | 
| May 29, 2025 | Land Evidence Date |