| Action Date | Action Description | 
|---|---|
| Aug 27, 1998 | Application Accepted | 
| Aug 27, 1998 | Category A* (Docks) | 
| Sep 02, 1998 | Historical Preservation Approval Granted | 
| Dec 23, 1998 | Plans Received | 
| Feb 09, 1999 | Engineering Report | 
| Feb 23, 1999 | Meeting Held | 
| Mar 09, 1999 | Meeting Held | 
| Mar 23, 1999 | Meeting Held | 
| Mar 29, 1999 | Council Approval Granted | 
| Mar 29, 1999 | Permit Approved | 
| May 27, 1999 | Legal Response/Decision | 
| May 27, 1999 | Land Evidence Date | 
| Sep 25, 2002 | Modification Request | 
| Sep 25, 2002 | Administrative Review for Completeness | 
| Sep 25, 2002 | Team Review for Completeness | 
| Sep 25, 2002 | Modification Request | 
| Sep 26, 2002 | 30 day Public Notice Issued | 
| Sep 27, 2002 | Dock sub-committee Approved | 
| Nov 01, 2002 | Modification Approved | 
| Jan 27, 2005 | Correspondence Mailed/Faxed/E-mailed | 
| Apr 18, 2005 | 30 day Public Notice Issued | 
| May 16, 2005 | US Army Corp of Engineers Permit Date | 
| May 17, 2005 | US Army Corps of Engineers Approval Received | 
| May 17, 2005 | Engineering Report | 
| May 18, 2005 | Public Notice End Date | 
| May 24, 2005 | Executive Sign Off | 
| Jun 03, 2005 | Ready to Schedule Semi-Monthly Meeting | 
| Jun 03, 2005 | Mail Agenda Notice | 
| Jun 14, 2005 | Semi-Monthly Meeting Held | 
| Jun 14, 2005 | Council Approval Granted | 
| Jun 14, 2005 | Semi-Monthly Meeting Date Scheduled | 
| Jun 17, 2005 | Stipulation Package by Engineer | 
| Jun 21, 2005 | Typist for Processing | 
| Jun 21, 2005 | Executive Sign Off | 
| Jun 21, 2005 | Sent to Photo Copy | 
| Jun 21, 2005 | Modification Approved | 
| Sep 09, 2005 | Land Evidence Date | 
| Sep 19, 2005 | Legal Response/Decision | 
| Sep 19, 2005 | Engineering Report | 
| Sep 19, 2005 | Executive Sign Off |