| Action Date | Action Description |
|---|---|
| Dec 23, 1999 | Application Accepted |
| Jan 10, 2000 | 30 day Public Notice Issued |
| Jan 12, 2000 | Historical Preservation Approval Granted |
| Feb 15, 2000 | Biologist Report |
| Feb 15, 2000 | Engineering Report |
| Feb 25, 2000 | Dock sub-committee Approved |
| Mar 01, 2000 | Permit Approved |
| Mar 01, 2000 | Land Evidence Date |
| Jan 28, 2022 | Modification Request |
| Feb 01, 2022 | Administrative Review for Completeness |
| Feb 03, 2022 | Bio Team Review for Completeness |
| Feb 03, 2022 | Project Manager |
| Feb 04, 2022 | Additional Information Received |
| Feb 09, 2022 | 30 day Public Notice Issued |
| Feb 11, 2022 | HPHC Review Pending |
| Feb 11, 2022 | HPHC Historical Preservation No Effect |
| Mar 08, 2022 | Objections/Comments Received |
| Mar 09, 2022 | Public Notice End Date |
| Jun 09, 2022 | Objection withdrawal received |
| Dec 19, 2022 | Correspondence Received |
| Feb 08, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Mar 09, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Mar 15, 2023 | Phone Call |
| Mar 16, 2023 | Mail Agenda Notice |
| Mar 20, 2023 | Additional Information Received |
| Mar 20, 2023 | Additional Information Received |
| Apr 12, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Dec 06, 2023 | Correspondence Received |
| Dec 06, 2023 | Correspondence Mailed/Faxed/E-mailed |
| Dec 21, 2023 | Additional Information Received |
| Jan 03, 2024 | 30 day Public Notice Issued |
| Jan 18, 2024 | Biologist Report |
| Feb 03, 2024 | Public Notice End Date |
| Feb 09, 2024 | Dock/1.1.6 Review approval |
| Feb 12, 2024 | Typist for Processing |
| Feb 12, 2024 | Executive Sign Off |
| Feb 12, 2024 | Sent to Photo Copy |
| Feb 12, 2024 | Modification Approved |
| Feb 19, 2024 | Permit Mailed |
| Mar 12, 2024 | Land Evidence Date |