| Action Date | Action Description |
|---|---|
| Jul 26, 2004 | Application Accepted |
| Jul 26, 2004 | 30 day Public Notice Issued |
| Aug 16, 2004 | Historical Preservation Approval Granted |
| Aug 26, 2004 | Category B assigned |
| Aug 26, 2004 | Engineering Report |
| Oct 10, 2004 | Biologist Report |
| Oct 12, 2004 | Meeting Held |
| Oct 26, 2004 | Permit Approved |
| Oct 26, 2004 | Land Evidence Date |
| Nov 03, 2004 | 30 Day Appeal Notification to Owner |
| Nov 09, 2004 | Council Approval Granted |
| Jan 11, 2005 | Extension of Permit Request |
| Jan 11, 2005 | Ready to Schedule Semi-Monthly Meeting |
| Jan 18, 2005 | Mail Agenda Notice |
| Jan 25, 2005 | Semi-Monthly Meeting Held |
| Jan 25, 2005 | Semi-Monthly Meeting Date Scheduled |
| Jan 25, 2005 | Council Approval - Extension Granted |
| Feb 02, 2005 | Extension Approved |
| Feb 02, 2005 | Typist for Processing |
| Feb 02, 2005 | Executive Sign Off |
| Feb 02, 2005 | Sent to Photo Copy |
| Nov 08, 2005 | Correspondence Received |
| Nov 29, 2005 | Correspondence Mailed/Faxed/E-mailed |
| Jan 03, 2006 | Correspondence Received |
| Jul 28, 2008 | Extension of Permit Request |
| Nov 12, 2008 | Correspondence Received |
| Nov 17, 2008 | Extension Approved |
| Nov 17, 2008 | Enforcement Compliance Inspection Required |
| Aug 26, 2009 | Extension of Permit Request |
| Oct 13, 2009 | Enforcement Compliance Inspection Required |
| Oct 23, 2009 | Process Extension |
| Oct 23, 2009 | Extension Approved |
| Sep 17, 2012 | Modification Request |
| Sep 18, 2012 | Administrative Review for Completeness |
| Sep 26, 2012 | Team Review for Completeness |
| Sep 26, 2012 | Engineering Report |
| Sep 26, 2012 | Typist for Processing |
| Sep 26, 2012 | Modification Approved |
| Sep 28, 2012 | Executive Sign Off |
| Sep 28, 2012 | Sent to Photo Copy |
| Jul 01, 2014 | Extension Toll letter mailed |
| Nov 12, 2015 | Extension Toll letter mailed |
| Jul 21, 2017 | Correspondence Mailed/Faxed/E-mailed |