| Action Date | Action Description | 
|---|---|
| Aug 18, 2004 | Application Accepted | 
| Aug 24, 2004 | Engineering Report | 
| Aug 31, 2004 | Permit Approved | 
| Aug 31, 2004 | Land Evidence Date | 
| Feb 01, 2021 | Modification Request | 
| Feb 12, 2021 | Administrative Review for Completeness | 
| Feb 25, 2021 | Bio Team Review for Completeness | 
| Feb 26, 2021 | Project Manager | 
| Mar 03, 2021 | HPHC Review Pending | 
| Mar 03, 2021 | HPHC Historical Preservation No Effect | 
| May 07, 2021 | 30 day Public Notice Issued | 
| Jun 07, 2021 | Public Notice End Date | 
| Jun 17, 2021 | Dock Meeting -- Approval | 
| Jul 16, 2021 | Plans Received | 
| Aug 05, 2021 | Stipulation Package from Biologist | 
| Aug 05, 2021 | Biologist Report | 
| Aug 06, 2021 | Typist for Processing | 
| Aug 06, 2021 | Executive Sign Off | 
| Aug 06, 2021 | Sent to Photo Copy | 
| Aug 06, 2021 | Modification Approved | 
| Jan 13, 2022 | Land Evidence Date |