| Action Date | Action Description |
|---|---|
| Mar 18, 2005 | Assent Application Received |
| Mar 24, 2005 | Administrative Review for Completeness |
| Apr 05, 2005 | Team Review for Completeness |
| Apr 05, 2005 | Application Accepted |
| Apr 05, 2005 | Category B assigned |
| Apr 14, 2005 | Correspondence Received |
| Apr 18, 2005 | HPHC Review Pending |
| Jun 15, 2005 | 30 day Public Notice Issued |
| Jun 16, 2005 | Additional Information Received |
| Jul 14, 2005 | Correspondence Received |
| Jul 15, 2005 | Objections/Comments Received |
| Jul 15, 2005 | Objections/Comments Received |
| Aug 05, 2005 | Correspondence Received |
| Aug 05, 2005 | Correspondence Received |
| Aug 15, 2005 | Public Notice End Date |
| Apr 21, 2006 | Correspondence Received |
| Jul 17, 2006 | Correspondence Received |
| Oct 30, 2006 | Correspondence Mailed/Faxed/E-mailed |
| Jul 11, 2007 | Additional Information Received |
| Jul 26, 2007 | Correspondence Received |
| Aug 07, 2007 | Correspondence Received |
| Aug 23, 2007 | Correspondence Mailed/Faxed/E-mailed |
| Aug 31, 2007 | Plans Received |
| Aug 31, 2007 | Correspondence Received |
| Nov 13, 2007 | Plans Received |
| Jan 02, 2008 | Mail Agenda Notice |
| Jan 10, 2008 | Correspondence Received |
| Jan 15, 2008 | Council Approval Granted |
| Jan 15, 2008 | Semi-Monthly Meeting Date Scheduled |
| Jan 22, 2008 | Biologist Report |
| Feb 20, 2008 | Historical Preservation Approval Granted |
| Feb 20, 2008 | Water Quality Certification |
| Feb 26, 2008 | Water Quality Certification |
| Mar 11, 2008 | Legal Response/Decision |
| May 23, 2008 | Correspondence Received |
| Sep 26, 2008 | Correspondence Mailed/Faxed/E-mailed |
| Dec 17, 2009 | Additional Information Received |
| Dec 23, 2009 | Permit Approved |
| Dec 23, 2009 | Stipulation Package from Biologist |
| Dec 23, 2009 | Stipulation Package by Engineer |
| Dec 30, 2009 | Conservation Easement Mailed. |
| Jan 05, 2010 | Conservation Easement Recording received |
| Jan 05, 2010 | Land Evidence Date |
| Oct 30, 2014 | Correspondence Received |
| Nov 13, 2014 | Correspondence Received |
| Dec 24, 2014 | Plans Received |
| Aug 07, 2018 | Modification Request |
| Aug 08, 2018 | Administrative Review for Completeness |
| Aug 28, 2018 | Team Review for Completeness |
| Aug 28, 2018 | Deficient Application - Owner Notification Sent |
| Oct 30, 2018 | Deficient Application Picked Up |
| Nov 07, 2018 | Deficiency Response Received |
| Nov 14, 2018 | Team Review for Completeness |
| Nov 16, 2018 | Application Accepted |
| Dec 12, 2018 | HPHC Historical Preservation No Effect |
| Apr 04, 2019 | Plans Received |
| Apr 12, 2019 | Extension of Permit Request |
| Apr 25, 2019 | Enforcement Compliance Inspection Required |
| Apr 25, 2019 | Process Extension |
| Apr 25, 2019 | Extension Approved |
| May 14, 2019 | Additional Information Received |
| May 16, 2019 | Biologist Report |
| May 16, 2019 | Engineering Report |
| May 17, 2019 | Typist for Processing |
| May 17, 2019 | Executive Sign Off |
| May 17, 2019 | Sent to Photo Copy |
| May 17, 2019 | Modification Approved |
| May 28, 2019 | Land Evidence Date |
| May 11, 2020 | Extension of Permit Request |
| May 14, 2020 | Enforcement Compliance Inspection Required |
| May 14, 2020 | Process Extension |
| May 14, 2020 | Extension Approved |