| Action Date | Action Description | 
|---|---|
| Jul 12, 2005 | Assent Application Received | 
| Jul 15, 2005 | Administrative Review for Completeness | 
| Jul 19, 2005 | Team Review for Completeness | 
| Jul 19, 2005 | Application Accepted | 
| Jul 19, 2005 | Additional Information Requested from Applicant | 
| Jul 26, 2005 | Biologist Report | 
| Jul 26, 2005 | Engineering Report | 
| Jul 26, 2005 | Typist for Processing | 
| Jul 26, 2005 | Executive Sign Off | 
| Jul 26, 2005 | Sent to Photo Copy | 
| Jul 26, 2005 | Permit Approved | 
| Jul 29, 2005 | Land Evidence Date | 
| Aug 15, 2005 | Correspondence Received |