| Action Date | Action Description |
|---|---|
| Jul 14, 2005 | Assent Application Received |
| Jul 15, 2005 | Administrative Review for Completeness |
| Jul 18, 2005 | Team Review for Completeness |
| Jul 18, 2005 | Application Accepted |
| Jul 25, 2005 | Deficient Application - Owner Notification Sent |
| Jul 29, 2005 | Deficiency Response Received |
| Aug 01, 2005 | Engineering Report |
| Aug 12, 2005 | 30 day Public Notice Issued |
| Aug 12, 2005 | Historical Preservation Approval Granted |
| Aug 12, 2005 | Historical Preservation Approval Granted |
| Aug 12, 2005 | HPHC Review Pending |
| Sep 12, 2005 | Public Notice End Date |
| Sep 15, 2005 | Dock Subcommittee Meeting Held |
| Sep 19, 2005 | US Army Corp of Engineers Permit Date |
| Sep 22, 2005 | US Army Corps of Engineers Approval Received |
| Sep 22, 2005 | Biologist Report |
| Sep 22, 2005 | Additional Information Received |
| Sep 26, 2005 | Typist for Processing |
| Sep 26, 2005 | Executive Sign Off |
| Sep 26, 2005 | Sent to Photo Copy |
| Sep 26, 2005 | Permit Approved |
| Nov 03, 2005 | Land Evidence Date |
| Aug 25, 2008 | Extension of Permit Request |
| Dec 05, 2008 | Enforcement Compliance Inspection Required |
| Dec 05, 2008 | Extension Approved |