| Action Date | Action Description |
|---|---|
| Aug 03, 2006 | Freshwater Wetland - Preliminary Determination |
| Aug 21, 2006 | Administrative Review for Completeness |
| Aug 21, 2006 | Team Review for Completeness |
| Aug 21, 2006 | Application Accepted |
| Sep 05, 2006 | HPHC Historical Preservation No Effect |
| Oct 12, 2006 | Typist for Processing |
| Oct 12, 2006 | Executive Sign Off |
| Oct 12, 2006 | Sent to Photo Copy |
| Oct 12, 2006 | Permit Approved |
| Oct 12, 2006 | Biologist Report |
| Nov 16, 2006 | Land Evidence Date |
| Nov 13, 2007 | Modification Request |
| Nov 14, 2007 | Administrative Review for Completeness |
| Nov 15, 2007 | Team Review for Completeness |
| Nov 24, 2007 | HPHC Historical Preservation No Effect |
| Feb 12, 2008 | Plans Received |
| Feb 14, 2008 | Biologist Report |
| Feb 15, 2008 | Typist for Processing |
| Feb 15, 2008 | Executive Sign Off |
| Feb 15, 2008 | Sent to Photo Copy |
| Feb 15, 2008 | Modification Approved |
| Feb 29, 2008 | Land Evidence Date |
| Oct 01, 2009 | Extension of Permit Request |
| Oct 21, 2009 | Enforcement Compliance Inspection Required |
| Oct 21, 2009 | Process Extension |
| Jul 16, 2014 | Extension Toll letter mailed |
| Jun 20, 2016 | Extension Toll letter mailed |