| Action Date | Action Description | 
|---|---|
| Dec 22, 2006 | Assent Application Received | 
| Dec 28, 2006 | Administrative Review for Completeness | 
| Jan 08, 2007 | Deficient Application - Owner Notification Sent | 
| Dec 06, 2007 | Additional Information Received | 
| Dec 18, 2007 | Application Accepted | 
| Jan 29, 2008 | Engineering Report | 
| Jan 29, 2008 | Typist for Processing | 
| Jan 29, 2008 | Executive Sign Off | 
| Jan 29, 2008 | Sent to Photo Copy | 
| Jan 29, 2008 | Permit Approved | 
| Feb 22, 2008 | Land Evidence Date | 
| Jan 31, 2011 | Extension of Permit Request | 
| Mar 10, 2011 | Extension Toll letter mailed | 
| Jul 13, 2012 | Extension Toll letter mailed | 
| Jul 25, 2012 | Correspondence Received | 
| Jul 18, 2013 | Modification Request | 
| Jul 19, 2013 | Administrative Review for Completeness | 
| Jul 19, 2013 | Team Review for Completeness | 
| Aug 06, 2013 | HPHC Historical Preservation No Effect | 
| Aug 27, 2013 | Additional Information Received | 
| Sep 11, 2013 | Typist for Processing | 
| Sep 11, 2013 | Modification Approved | 
| Sep 11, 2013 | Biologist Report | 
| Sep 12, 2013 | Executive Sign Off | 
| Sep 12, 2013 | Sent to Photo Copy | 
| Sep 23, 2013 | Land Evidence Date |